Fully Burdened Cost
Fully burdened cost is defined by the formulas in this section.
Fully Burdened Cost per Part =
Total Cost + Amortized Investment
Fully burdened cost is defined in the rollup module. It is the sum of the following per part costs:
-
Total cost (also known as “Piece Part Cost”. See the formula below)
-
Amortized investment (see Amortized Investment)
Total Cost = Margin + Piece and Period
-
Margin: by default it is the product of piece and period and the value of the cost model variable marginRate.
-
Piece and period (see the formula below)
Piece and Period = Piece Cost +
Indirect Overhead Cost + SG&A
Piece and period is defined in the Site cost model global taxonomy module. It is the sum of the following per part costs:
-
Piece cost (see Piece Cost)
-
Indirect overhead cost (also known as “period overhead”--see Overhead Costs per Part)
-
SG&A: this is the per part cost for SG&A (sales, general, and administration). By default this is the product of the piece cost and the value of the cost model variable sgaPercent.